SoftBank Loss of $7.1bn Puts a Cap on AI Gas Power Ambitions

SoftBank has taken a large hit on its bet that natural gas would power the AI boom. The Japanese group reported a $7.1 billion quarterly loss on Tuesday, and more than half of it, over $3 billion, was linked to power generation equipment. The SoftBank loss may put a ceiling on plans to run AI data centres on gas, according to TechCrunch.

How the bet went wrong

SoftBank invested $30 billion in OpenAI in early 2025 and then moved into energy to support AI computing. In February 2026, its subsidiary SB Energy announced a $33 billion, 9.2-gigawatt natural gas power plant.

About two years ago, SoftBank reportedly placed deposits on more than 13 gigawatts of gas turbines, roughly 50 percent more than it needed, according to the Wall Street Journal. Chief executive Masayoshi Son reportedly wanted to control a large share of gas power supply for AI data centres.

The deposits were nonrefundable. SoftBank now considers much of that money lost, and it accounts for a large part of the quarterly charge.

Why companies overbooked turbines

Demand for gas turbines has surged as data centre developers look for fast power. Delivery queues now stretch into the early 2030s. Peter Gardett, chief executive of Noreva, said SB Energy had little choice but to overbook to get some turbines quickly. “This charge is just that price discovery finally happening,” he said.

Grid and batteries as the alternative

Brent Nelson, senior managing director for markets and strategy at Ascend Analytics, told TechCrunch’s Equity podcast that most data centres are better served by grid connections, ideally smaller ones, paired with large batteries.

Gas has its own risks. Supply can dip in winter and demand spikes can lead to curtailment. Hyperscalers turned to gas mainly because grid connections can take years to approve. TechCrunch’s analysis is that SoftBank’s losses are unlikely to cause mass cancellations of gas plants, because AI’s power needs remain huge.

Lessons for Pakistan

Pakistan is trying to attract data centre investment, and power is one of the biggest obstacles because of high tariffs and grid reliability. The SoftBank case shows that energy planning for AI is expensive and risky even for the richest investors. The government has been weighing special electricity rates for digital infrastructure, as ITInsider reported on the industrial power tariff proposal for telecom.

Key facts

  • SoftBank reported a $7.1 billion quarterly loss on November 10.
  • More than $3 billion of the loss was tied to power generation equipment.
  • SB Energy announced a $33 billion, 9.2-gigawatt gas plant in February 2026.
  • SoftBank reportedly reserved over 13 GW of turbines, about 50% more than needed.
  • Turbine delivery queues now run into the early 2030s.

FAQ

Why did SoftBank lose money?

A large part of its $7.1 billion quarterly loss came from nonrefundable deposits on gas turbines it no longer expects to use.

Will AI data centres stop using gas?

Unlikely. Analysts quoted by TechCrunch say AI’s power demand is still so large that gas plants will keep being built.

What is the alternative to gas?

Some analysts say smaller grid connections combined with large battery storage suit most data centres better.

Official sources: SoftBank Group (quarterly results)

Also reported by: TechCrunch

Facts and figures checked against official sources by the ITInsider desk.

Featured image: representational, AI-generated

Previous Post
Next Post

Latest News

  • All Posts
  • AI & Tech
  • E-commerce
  • Events
  • Freelancing & Jobs
  • Industry
  • Interviews
  • IT Exports
  • ITInsider Research
  • News
  • Policy & Govt
  • Startups & Funding
  • Telecom & Digital
  • World Tech
    •   Back
    • IT Pulse
    • Company Lens
    • Policy Check
    • Sector Deep Dive

NEWSLETTER

The Weekly IT Briefing

    Edit Template