The Prime Minister’s Office has asked a special task force to finalise its recommendations on an industrial electricity tariff for telecom operators, including the financial cost and a way to cover the tariff difference, Business Recorder reported on 11 November 2026. The move follows a joint letter to Prime Minister Shehbaz Sharif from the chief executives of Jazz, Zong (CMPak), PTML (Ufone and Telenor) and PTCL.
The operators say their towers, switching centres and data centres still pay commercial power rates even though telecom has been treated as an industry in policy and tax law. They argue that cheaper power would free money for 5G, fibre and AI-ready data centres.
Key facts
- Who asked: CEOs of Jazz, Zong, PTML (Ufone and Telenor) and PTCL, in a joint letter to the Prime Minister
- What the PMO did: told the task force, working with the Power and Finance divisions, to finalise recommendations, costs and a mechanism to absorb the tariff differential
- Task force: formed on 29 June 2026 under the MoITT Secretary; first meeting on 4 August 2026
- Members: PTA Chairman, Power Division, NEPRA, DISCOs, telecom operators and MoITT’s Member Telecom
- Cost pressure cited by operators: commercial power tariffs for telecom sites up about 197 percent since 2018, fuel costs up about 300 percent, ARPU down about 22 percent
- Investment pledge: about $2 billion over three years for 5G and fibre, plus Tier-III data centres
Why telecom operators want an industrial power tariff
Electricity is one of the biggest running costs for a mobile network. Every tower, exchange and data centre runs around the clock, and many sites keep generators and batteries for load-shedding. According to the operators’ letter, as reported by Business Recorder, power tariffs on telecom sites have risen about 197 percent since 2018 and fuel costs about 300 percent. Over the same period, average revenue per user fell about 22 percent, and operators also carry an extra five percent withholding tax.
The CEOs said rising consumption from 5G and AI services makes commercial tariffs increasingly unsustainable. They have committed about $2 billion over the next three years to 5G deployment and fibre expansion, and they are also building AI-ready data centre capacity.
The legal and policy case
The operators point to several documents. The Mobile Cellular Policy 2004 and a Ministry of Industries notification of 20 April 2004 treated telecom as an industry. The Finance Act 2021 amended the Income Tax Ordinance to include PTA-licensed operators in the definition of an industrial undertaking. They also cite NEPRA’s 2018 decision to give dairy and poultry farms industrial tariffs.
Most directly, the MoITT policy directive of 6 January 2026 for the IMT spectrum auction mandated a joint task force to examine industrial tariffs for telecom, along with smart-grid solutions and dedicated feeders to cut long outages. That is the task force now being asked to finish its work.
What it means for users and the grid
If approved, cheaper power could lower operators’ costs and, in their words, be redirected to 5G, rural coverage and fibre-to-the-home. Operators also argue it would help power distribution companies: industry projections say that growth of off-grid solar at telecom sites could fall from about 15 percent to 5 to 7 percent, while grid use could rise by 15 to 20 percent, offsetting lost revenue in two to three years. These are the industry’s own projections and have not been independently checked.
The cost question remains open. Any tariff difference has to be absorbed somewhere, either by the budget, by other consumers or through higher grid sales. That is exactly what the PMO has asked the task force to quantify before the federal government decides.
The decision also connects to wider connectivity goals. Spectrum is no longer the main constraint after the March 2026 auction, so running costs and power reliability are now among the biggest factors in how fast networks expand. On the same day, the IT minister said Pakistan internet speed is up about 60 percent and 5G users have reached 1.8 million.
FAQ
Has the government approved industrial tariffs for telecom?
No. The PMO has asked the task force to finalise recommendations, including costs, for the federal government to consider.
Who would benefit?
Licensed telecom infrastructure such as cell towers, switching centres and data centres, according to the operators’ request.
When will a decision come?
No date has been reported. The next step is the task force’s final recommendations to the government.
Official sources: Ministry of IT and Telecommunication, Pakistan Telecommunication Authority, NEPRA
Also reported by: Business Recorder
Facts and figures checked against official sources by the ITInsider desk.
Featured image: representational, AI-generated